1. X is twice good a workman as Y and together they finish a piece of work in 18 days. In how many days will X alone finish the work ?
Solution - According to the condition given if X is twice good a workman as Y then the time taken by X to finish a particular work would be half of the time taken by Y to finish the same work.
So if we suppose that Y takes 2k days to finish a work then X would take k days to finish the same work.
Solving, 1/(2k) + 1/(k) = 1/18
k = 27 days
Answer - X would finish the work in 27 days.
2. If 10 men complete a work in 12 days. How many days would be taken by 18 men to complete the same work ?
Solution - Suppose the time taken by 18 men to complete the same work is t days.
Using the concept of Mandays -
10*12 = 18*t
t = 20/3 days
Answer - 18 men would take 20/3 days to complete the same work.
3. If 100 men can do 100 jobs in 100 days, 1 men can do one job in how many days ?
Solution - Using the concept M*D = W
(100*100)/(1*D) = 100/1
Solving we get D = 100 days
Answer - 1 men can do one job in 100 days.
4. 1 man or 2 boys or 3 girls can do a piece of work in 121 days. In how many days can one man, one girl and one boy do the same work ?
Solution - Let one man does m units of work in 1 day.
Let one boy does b units of work in 1 day.
Let one girl does g units of work in 1 day.
So 1m*121 = 2b*121 = 3g*121 = W, where W is the total units of work.
m = W/121 , b= W/242 , g = W/ 363
So 1 man, 1 girl and 1 boy can do the same work in (W) / ((W/121) + (W/242) + (W/363)) = 66
Answer - So 1 man, 1 girl and 1 boy can do the same work in 66 days.
5. If the ratio of work efficiency of P & Q is 6:5 and that of Q & R is 6:5. If P can complete the piece of work in 2 days, In how many days the same work can be completed by Q & R separately ?
Solution - If the work efficiency of P & Q is 6:5 then time taken would be in the ratio 5:6
If the work efficiency of Q & R is 6:5 then time taken would be in the ratio 5:6
Let the time taken by P = 5K and by Q = 6K, where K is some constant.
5K = 2, So 6K = 12/5 Days
So the time taken by Q to complete the work is 12/5 days
Now let the time taken by Q = 5X and by R = 6X, where X is some constant.
Q = 12/5 days, So R = 72/25 days
Answer - So the time taken by R to complete the work is 72/25 days.